The private housing reconstruction process continues in the 14 most affected districts. As of June 26, 2017 28,019 houses have been rebuilt and 63,902 are under construction.
The Government of Nepal has also started the distribution of first tranche in the 17 less affected districts and has agreed to provide support to landless quake survivors and people living in vulnerable settlements by developing integrated settlements. Finally, to strengthen technical support on the ground, 27 engineers hired by UNDP for the NRA have been deployed to apply their expertise in implementing the recently approved Corrections / Exceptions Manual which simplifies the technical procedures without compromising on quality of construction.
Below a summary of the latest data on the program's key indicators.